Summer 2026 Renovation Update

Sep 7
1 min read

This summer marked an important milestone in St. Paul’s renovation project as plans moved from preparation into active construction.


In June, the Vestry approved a contract with Chambliss & Rabil for a new narthex bathroom. Before construction could begin, asbestos abatement was required in the narthex, with remediation work starting on June 29.


By early July, portions of the narthex had been sealed off and some church entrances were temporarily unavailable while the work was underway. The asbestos remediation was completed later that month.


On July 23, St. Paul’s reported that the narthex bathroom design needed to be revised before construction could continue. Updated plans and additional permitting were therefore required.


Despite these early adjustments, the summer represented a significant step forward for the renovation, laying the groundwork for future improvements including better accessibility, larger restrooms, and an elevator.

Recent Posts

See All
Spring 2026 Renovation Update

Spring 2026 marked an important transition in St. Paul’s renovation project as years of planning began to translate into visible changes around the campus. One of the first signs came in February, whe

 
 
 

Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.
bottom of page